The boys' hall |
All the drywall is up. I hesitate to say the drywall is done because taping still need to happen. I don't know if taping is considered part of this phase or if it happens later. The project areas are looking different:
|
Bathroom looks more finished with drywall |
|
Bathroom closet (looking more like a niche) |
|
The north wall used to have a vent. |
|
|
Ceiling over the studio with the shed window and part of fireplace |
Larry left a note that the drain finally arrived. Remember, the project was delayed nearly two weeks because the drain was delayed. The plumber will return to install it this week yet, which means the tile and concrete work should stay on schedule.
No comments:
Post a Comment